Die casting mold development starts with the part drawing and leads to a machined steel die running on a casting machine. Before that run, the buyer and toolmaker agree on the part requirements, release the die design and check the assembled tool.
The tool shop first makes the steel die and fits its moving parts. The casting shop then uses the die to make the aluminum component. In the cold-chamber casting cycle, molten aluminum is transferred to the injection system and forced into the closed die. After solidification, the die opens and ejects the casting. The runner, overflows and flash can be removed in trimming before any secondary operations.
At each handoff, ask for the record the next team will work from. The toolmaker needs the released drawing before machining. The trial team needs the die revision, the agreed checks and a list of anything the design review left open.

What should you send before die casting mold development starts?
Send the controlled 2D drawing and 3D model, the specified alloy, expected volume and the features that must pass inspection. Identify which surfaces will be machined, sealed or finished after casting so the toolmaker can design for the required delivery condition.
Mark the faces where a witness mark would matter and identify the assembly datums on the drawing. If a sealing face will be machined, agree where the casting needs extra stock. The NADCA tooling guidance on secondary operations also calls for a discussion of pressure tightness and areas where machining might expose internal porosity.
Tell the toolmaker which press is intended for production. The machine’s rated clamping force is one input. Ask the supplier to confirm the actual machine interface, including mounting, shot and ejection arrangements, before releasing the die design. Record who can approve changes to the part or to the acceptance plan.
What should the die design review settle before steel is cut?
Use the die design review to settle the orientation, parting line and moving parts, along with the layout for filling, venting and cooling. The approved die design should identify the selected layout and any checks deferred to the first trial.
Start the DFM review with the part itself. Check deep features against the intended pull direction. On a sealing face, look at where the parting line and gate would leave a mark. Review draft, wall thickness, machining stock and the locations of cores and slides while the part and die models can still be revised.
In the mold design review, check the two die halves, inserts, runners, gates, overflows, vents, cooling and ejectors as a system. Record the simulation assumptions and the expected behavior when they guide a design choice, then note what the trial team should verify on the actual castings. A separate die casting mold risk assessment explains how to carry those open items into the trial.


How are the core, mold base and auxiliary parts made?
The tool shop plans rough machining, heat treatment, finishing and inspection around the function of each component. A cavity insert needs its casting geometry and working surfaces, while a mold base needs the seating and guiding features that locate and support the moving assemblies.


On a core or slide, the shop may drill access holes or cooling passages, then rough-machine the steel with allowance for later finishing. Choose the steel grade and heat-treatment requirement for the component’s duty. Recheck the reference faces after heat treatment. Set up the finishing operation from the datums on the tool drawing.


Use milling where the cutter can reach the feature. Raidy’s machining sequence also uses sinker EDM for recessed features and wire EDM for profiles with a clear wire path. Polish or finish selected surfaces to their specified function, then check the critical dimensions and fits before sending parts to assembly.



On the base, check support faces, guide positions and the location of the insert seats. Plan auxiliary parts individually. A round pin may need grinding, and a shaped insert may need CNC or EDM. For a sprue bushing, check the mating diameter and coaxiality against its drawing. When reviewing a block base, runner cone, cooling jacket, guide rail, clamp plate or wear plate, ask for the inspection results for the surfaces that locate or mate with other parts.



What does the toolmaker check before the first shot?
Before running metal, verify the assembled die for fit, smooth slide and ejector movement, and clear cooling circuits with the specified leak or pressure checks. Resolve tooling and machine setup issues before judging cast samples.
Check the parting faces where the two halves close, then check how the core seats in the base. Operate the slides and ejectors and confirm that they return as specified. Match the cooling connections and other interfaces to the released tool drawings. Assembly verification gives the trial team a record to consult if a problem appears under casting pressure or at operating temperature.
The first shot adds evidence from actual operation. Record how the die fills and releases the casting, then inspect selected samples against the agreed criteria. Carry any correction into the next run with the tool revision and the inspection evidence needed to accept the change. The mold trial guide covers sampling, reports and production approval in detail.

What should you receive at each development milestone?
Ask for the approved drawing, manufacturing checks and trial evidence at the points where they are used to make decisions. At handover, confirm what has been accepted and who owns the remaining actions.
Ask what currently sets the delivery date. It could be a drawing approval, steel procurement, a heat-treatment operation or the next available trial slot. Late design decisions or another round of corrections can affect the delivery date, so ask the supplier to show which stage must finish before the next can start.
For supplier comparisons, ask who handles simulation, machining, dimensional checks and machine trials. Review a sample of the inspection and traceability records, confirm any project-required quality certification and check the supplier’s experience on comparable aluminum tools. Before shipment, agree what travels with the die, including the released files, inspection records and maintenance information.
| Milestone | Ask to receive | Check before proceeding |
|---|---|---|
| Part review | Controlled part drawing and acceptance requirements | Alloy, machined and cosmetic areas, critical features and sample conditions are agreed. |
| Die design release | Approved tool layout and open decisions | Parting, core movement, fill, venting and thermal design have been reviewed. |
| Machining and assembly | Material, dimensional and functional checks | Interfaces fit, moving parts operate and cooling circuits meet the agreed checks. |
| First shot and corrections | Traceable trial castings and an action list | Each finding has a proposed action, owner and verification step. |
| Delivery | Agreed release and maintenance documents | The customer understands what was approved and any conditions still open. |

FAQ
When does casting start during die casting mold development?
The first casting can be made after the die has been assembled, checked and set up on the machine. In a cold-chamber aluminum process, the machine injects molten metal into the closed steel die for that first shot.
Do all the parts of a die casting mold use the same steel?
Tool steel selection depends on the part’s role and duty in the mold. The cavity insert and mold base serve different functions, so check the material specification by component.
When can a toolmaker give a reliable delivery estimate?
The toolmaker can give a firmer estimate once the part revision and die layout are agreed and the machining and trial sequence is known. Ask which approval or booked operation could still move the date.
What should you approve after the first shot?
Review the tool operation and sample checks planned for that run. Agree what can advance and what still needs correction, another run or customer approval.